Pooler Parkway Gets One More Holiday Season Before the Mill Creek Signal Changes

Pooler Parkway Gets One More Holiday Season Before the Mill Creek Signal Changes

"We are going to work to make sure that it is after the holiday shopping season and other things that happen around the holidays." Pooler's city manager said that to City Council on October 19, 2026, according to the Open Publica transcript of the meeting. He was describing the new construction contract for Pooler Parkway between the I-95 southbound ramps and Benton Boulevard.

That same night the council voted unanimously to give the job to Astra Group LLC for $4,312,700, subject to approval by the city attorney. Construction is "not anticipated to begin until early 2027."

So the stretch of Pooler Parkway most people take to Tanger Outlets, the Walmart off Mill Creek Circle and the interstate gets one more holiday season as it is now. Once the work is finished, one of its signals will work very differently.

The Stretch Between Exit 104 and Benton Boulevard

The project covers about 3,725 linear feet of Pooler Parkway, from the I-95 southbound ramps west to Benton Boulevard. The city's bid documents list roadway work, changes to the signalized intersections, sidewalks and drainage.

Three intersections are in play:

  • The I-95 southbound ramps at Exit 104. This is the eastern end of the project.
  • Mill Creek Circle and the Walmart driveway. This signal sits in the middle and changes the most.
  • Benton Boulevard and Tanger Outlets Boulevard. On the city's right-of-way plans, the two roads meet Pooler Parkway at the same intersection. That puts the entrance to Tanger Outlets Savannah, at 200 Tanger Outlets Blvd., at the project's western end.

The main change is capacity. Leon Davenport of Thunderbolt Consultant briefed the council on the design. He said it adds a third through lane in each direction, starting at the I-95 off-ramp and running "all the way through until you get to the Benton Boulevard intersection."

Benton Boulevard and Mill Creek Circle will also get more turn lanes. Davenport said the current layout is "a little restrictive."

What Changes at the Mill Creek Circle Signal

Today the Mill Creek Circle signal is a full-access intersection. Davenport put it this way: drivers leaving the retail on either side can "go straight across, make left turn movements um or or right turn movements."

The new design is what traffic engineers call an R-cut. Here is how the transcript describes it:

  • Right turns in: allowed from both sides.
  • Right turns out: allowed from both sides.
  • Left turns in: allowed, controlled by the signal.
  • Driving straight across from one retail side to the other: no longer possible, because it will "no longer" be "a full access intersection."
  • Left turns out onto Pooler Parkway: dropped, since right turns are the only way out at this signal.

In practice, the trip that changes most is the one that leaves the Walmart side or the shops across from it and heads the other way on Pooler Parkway. Davenport tied that trip directly to the Benton Boulevard work. He said the turn lanes added there "will allow for that egress, if you will, from those sites to get back out on Pooler Parkway and make those left turn movements they need to make."

The reason is signal time. Davenport said dropping the extra movements at Mill Creek helps "the cycling of that intersection and allow that through traffic movement uh to occur in a much smoother fashion." He named the afternoon traffic coming off I-95 and from the airport, including "our Gulf Stream friends," as the source of the worst backups.

Why the Start Date Moved Past the Holidays

The schedule is 18 months, so the project can't avoid every holiday season. Davenport said it plainly: "we will hit a holiday season. Uh it was just better to hit one instead of two."

Starting this fall would have put crews on the road through two holiday shopping seasons. Starting in early 2027 means they'll be there for one, the 2027 season, and this year's shopping happens on the road as it is now.

Even during construction, the parkway stays open. The bid documents require existing roads to remain open to traffic at all times, and the contractor needs a city-approved traffic control plan before work begins.

The state is paying part of the cost. Davenport told the council that GDOT Commissioner Russell McMurray committed about $2 million. He said the state benefits because the work should cut the daily backups down the I-95 ramp, which he called "a true safety hazard for vehicles on the interstate."

Astra Group was the lowest of four bids. The others were Reeves Construction Company at $4,934,939, JA Long Inc. at about $5.13 million and CW Matthews Contracting Company at about $6.67 million.

Astra's figure also includes a $400,000 field allowance. Davenport said that money isn't the contractor's, and the city hopes not to spend it.

The Rest of Pooler Parkway Is Already Under Construction

The Exit 104 project is the third Pooler Parkway job on the city's list. The other two are already underway, so in 2027 drivers will pass work zones at several points along the parkway.

Project

Contractor

Scope

Latest city status

Pooler Parkway at Quacco Road, Phase I

Astra Group LLC

About 1.5 miles of Quacco Road widened to four lanes, with turn lanes, shared-use paths and new signals

25% complete, on schedule, completion listed for July 2027

Pine Barren Road at Pooler Parkway

JA Long

About 3,200 feet of roadway with new signals, sidewalks, a multi-use trail and drainage

Sitework began in March 2026 on an 18-month schedule

Pooler Parkway at I-95, Mill Creek Circle and Benton Blvd.

Astra Group LLC

Third through lane each way, more turn lanes, R-cut at Mill Creek

Awarded Oct. 19, 2026; work expected early 2027

The Quacco Road project is the largest of the three. The city's capital projects page lists its construction cost at $19,229,000, with work that started in May 2025.

The city's Quacco Phase I FAQ says it is funded by SPLOST, the city's general fund and state and federal transportation money. SPLOST covers the local match the state and federal dollars require.

Planning for the next phase has started. On March 16, 2026, the council approved an $883,500 contract with Kimley-Horn for conceptual design, right-of-way plans and construction plans for Quacco Road from East Haven and Spanish Moss Crescent to the I-95 overpass.

At Pine Barren Road, the city's March 2026 sitework notice said early work should have little effect on traffic. Heavier construction was expected to start toward the end of the school year. The project is budgeted at about $4.4 million.

Key Dates for Driving to Tanger

Between now and the first lane shift at Exit 104, the busiest dates on the parkway are seasonal ones. Several of them lead straight to the Benton and Tanger Outlets Boulevard intersection at the west end of the project.

  1. Saturday, Nov. 21. Tanger on Ice opens at Tanger Outlets Savannah, with skating starting at 3 p.m. Admission is $18 per skater including skate rental, plus a $1.50 fee and tax. A season pass is $99 plus fee and tax.
  2. Mondays from Nov. 30 to Dec. 28. The rink drops to $15 plus fee and tax on Nov. 30 and Dec. 7, 14, 21 and 28.
  3. December. The City of Pooler calendar lists Santa Visits Pooler for December, 6 to 9 p.m., on "All streets."
  4. Sunday, Jan. 3, 2027. Tanger on Ice ends its season.
  5. Early 2027. Astra Group is expected to start work on Pooler Parkway between I-95 and Benton Boulevard, on an 18-month schedule.
  6. July 2027. The city's listed completion date for Quacco Road Phase I.

The city's events calendar says listings can change because of weather or scheduling conflicts. Check it again closer to each date.

The Tanger lot was also the center of Pooler's fall calendar, as we covered in Why Pooler's Fall Weekends Keep Ending Up at Tanger Outlets. For more on the city as a whole, see our Pooler neighborhood guide.

Road projects like these change how close a home really is to the interstate, the outlets and everyday errands. At Robin Lance Realty, we follow the details because our clients ask about their drive as often as they ask about the house. If you own near the Pooler Parkway corridor and want to know where your home stands before construction starts in 2027, get your home value and we'll walk you through it.

Partner with Our Expert Team

We listen carefully to understand each client’s real estate goals and work hard to create solutions that make sense. Whether new to the market or an experienced investor, we have the expertise, proven track record, and resources to help our clients accomplish their real estate objectives.

Follow Me on Instagram